Scheduling
Second unit
Also called 2nd unit
What is second unit in film production?
A second unit is a smaller, separate crew that shoots material not needing the principal cast or the director — establishing shots, inserts, cutaways, driving plates, stunts — often on the same day as the main unit, under a second unit director who works to the director's plan.
Because the two units shoot at the same time, a schedule has to hold both without reading them as a clash: Day 12 for the main unit and Day 12 for the second unit are two different days of work, with their own call sheets, locations and crew. Treating the second unit as its own day is also what keeps its cost visible rather than buried in the main unit's.
How big a second unit is varies enormously — from a camera operator and an assistant grabbing inserts to a full action unit with its own stunt team. On many smaller productions there is none, and its shots are picked up by the main unit at the end of the schedule.
Go deeper
Reviewed